At the end of March 2006 WoodWisdom-Net completed the process leading up to a decision regarding the areas of the coming Calls for Proposal, and three working groups are now planning the launch. More information available in the latest Newsletter in http://www.woodwisdom.net/publications/. You can follow the process via the WoodWisdom-Net website http://www.woodwisdom.net and you can also subscribe to the WoodWisdom-Net eNewsletter by email woodwisdom.office@woodwisdom.fi
The consultation project is carried out through the following tasks:
| Task | Participants | Tentative schedule |
| 1. Solicitation of research issues | Researchers | 15.7-15.10.05 (Closed) |
| 2. Assessment of research issues | Researchers | 29.11.05-18.1.06 (Closed) |
| 3. Identification of networks | Project team | In process |
| 4. Assessment of research issues | Industrial leaders and commentators | 13.1-1.2 (Closed) |
| 5. Initial screening of research issues | Project team | 1-2/06 (Closed) |
| 6. Workshops for researchers and industrial leaders | 10-12 researchers and industrial leaders / workshop | 14-16.2.06 (Closed) |
| 7. Workshop for funding organisations | Representatives from funding organizations | 28.3.06 (Closed) |
| 28.3.2006 | Workshop for funding organisations (Task 7) were organized in Vantaa Finland. |
| 1.3.2006 | Results from the workshops for researchers and industrial leaders are now analyzed. |
| 14-16.2006 | Three workshops (Task 6) were organized in Helsinki Finland, where set of researhers and industrial leaders discussed on the solicited issues and the analysis |
| 6.2.2006 | Multi-criteria analysis (Task 5) for solicited issues is now carried out in Helsinki University of Technology. |
| 1.2.2006 | Task 4 closed |
| 18.1.2006 | Task 2 closed |
| 3.1.2006 | Task 4 opened |
| 3.1.2006 | Task 2 open until 15.1.2006 |
| 29.11.2005 | Task 2 opened |
| 20.9.2005 | Tentative schedule changed. Task 1 open until 15.10.2005, See also other tasks schedules. |
| 23.8.2005 | Contact information of the registered participants added |
| 15.7.2005 | Task 1 opened for participation |
| 12.7.2005 | Site opened |